Construction Status

Wintergreen
As on 30thSeptember 2020

All illustrations and pictures are artistic impressions only

Construction Status

Wintergreen
As on 30thSeptember 2020
Wintergreen A-Wing
A Wing Construction Pics 1
Meter Shaft SFU installation & Wire termination work by TATA power in progress
A Wing Construction Pics 2
3rd floor Flat DEF toilet dado work
A Wing Construction Pics 3
5th to 25th floor ply fixing in electric duct completed.
A Wing Construction Pics 3
Lobby False Ceiling - 1) Framing done from 5th to 42nd floor. 2) Gypsum board fixing from 5th to 24th floor
A Wing Construction Pics 4
Internal Putty Work done on 41AB,36A,35ABCDEF one coat of putty done.
A Wing Construction Pics 6
5th to 12th floor Servant toilet Waterproofing Blockbat done
A Wing Construction Pics 7
Refuge floor waterproofing work on 15th, 29th and 36th floor completed.
A Wing Construction Pics 7
27th,28th, 31st, 35th to 37th floor door shutter installation work in progress.(90% work done)
A Wing Construction Pics 7
42nd floor - staircase tiling work

Disclaimer

These are the actual images that have been captured and displayed only for information.

Wintergreen B-Wing
B wing Construction Pic 1
1) False Ceiling framing done from 1st to 7th floor. 2) Gypsum Board fixing completed from 3rd to 6th floor
B wing Construction Pic 2
1st floor kitchen dado work
B wing Construction Pic 2
1st floor deck area waterproofing-chemical Coat

Disclaimer

These are the actual images that have been captured and displayed only for information.

Wintergreen C - Wing
B wing Construction Pic 3
C wing – Fire plant room pumps shifted on foundation
C wing Construction Pic 1
3rd to 11th floor - Lobby false ceiling framework completed.
D wing Construction Pic 1
3rd floor gypsum repair above skirting

Disclaimer

These are the actual images that have been captured and displayed only for information.

Wintergreen D-Wing
D wing Construction Pic 2
Wing D – Meter Shaft SFU installation & Wire termination work by TATA power in progress
D wing Construction Pic 3
Staircase tread and riser from 21st to 25th floor. Landing & midlanding in Progress
D wing Construction Pic 4
Metal door fixing from 3rd to 42nd floor completed in Lobby ( LV-1, Fire-2, Bus Riser-1, Meter room-1/Floor)
D wing Construction Pic 5
4th to 42nd floor – Servant toilet basecoat and plaster completed
D wing Construction Pic 6
Lift 5 architrave frame work ( inside Only) 25th to 42nd floor completed.
D wing Construction Pic 6
Window shutter installation work in progress
D wing Construction Pic 6
3rd and 4th floor - toilet dado Work in progress
D wing Construction Pic 6
Lobby False Ceiling grid work 16th to 34th floor completed.

Disclaimer

These are the actual images that have been captured and displayed only for information.

Wintergreen E-Wing
E wing Construction Pic
1st floor-Flat 1 to 7- deck area blockbat waterproofing completed
E wing Construction Pic
1st floor gypsum Panning work
E wing Construction Pic
False ceiling framing completed from 1st to 7th floor, gypsum board fixed on 2nd, 3rd floor.
E wing Construction Pic
1st floor all flat ( 8 no's) toilet and main flooring completed.
E wing Construction Pic
1st floor - deck area waterproofing
E wing Construction Pic
1st floor - false ceiling grid work

Disclaimer

These are the actual images that have been captured and displayed only for information.

Wintergreen F-Wing
F wing Construction Pic 1
F wing – Fire plant room testing work in progress
F wing Construction Pic 1
Wing F – terrace level fire booster pump installation in progress
F wing Construction Pic 1
F wing – Plumbing shaft, PRV installation in progress.
F wing Construction Pic 1
3rd to 6th floor and on 9th floor 1 coat of putty done.
F wing Construction Pic 1
Refuge floor Waterproofing basecoat done on 7th, 9th floor and 11th floor- Chemical Coat Done.
F wing Construction Pic 1
Door shutter installed on 9th, 10th and 11th floor.
F wing Construction Pic 1
3rd floor kitchen shaft –Shera Board fixing done
F wing Construction Pic 1
F wing Lobby false ceiling gypsum board fixing done from 3rd to 11th floor

Disclaimer

These are the actual images that have been captured and displayed only for information.

Wintergreen Podium
F wing Construction Pic 1
Podium 1 – Fire alarm smoke detectors back box installation in progress
F wing Construction Pic 1
Podium 2 – HVAC works, Axial fans installation in progress
F wing Construction Pic 1
Podium 2 – E wing electrical meter room work in progress
F wing Construction Pic 1
Podium 2 – F wing electrical meter room work in progress
F wing Construction Pic 1
Podium 2 – C wing electrical meter room work in progress
F wing Construction Pic 1
Podium 2 – B wing electrical meter room work in progress
F wing Construction Pic 1
Podium 2 – A wing, Panel room cable tray installation completed
F wing Construction Pic 1
Podium 0 – External area, landing valve installation completed
F wing Construction Pic 1
Podium 3 – Fire fighting, deluge valve installation in progress
F wing Construction Pic 1
P1 – Surface drain piping in progress.
F wing Construction Pic 1
Podium 1 – Bus duct connection to end feed unit work in progress
F wing Construction Pic 1
Podium 1 – LA CI class pipe installation near wing A
F wing Construction Pic 1
PODIUM – WING C TO WING D PLANTER WATERPROOFING WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING C TO WING D PLANTER WATERPROOFING WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING C TO B CFO DRIVEWAY WATERPROOFING PREPARATION WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING C TO B CFO DRIVEWAY WATERPROOFING WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING E TO F COURTYARD CFO DRIVEWAY WATERPROOFING WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING D TO E COURTYARD CFO DRIVEWAY FILLING WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING C TO D CFO DRIVEWAY FILLING WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING E LIFT LOBBY FILLING WORKS IN PROGRESS
F wing Construction Pic 1
PODIUM – WING A CFO DRIVEWAY RCC WALLS CASTING DONE

Disclaimer

These are the actual images that have been captured and displayed only for information.

Privacy Statement | Disclaimer | Designed by 2 Tech Brothers

(c) 2020 Rivali Park. All Rights Reserved

Drop Your Query
Submit